Future Plans
VIBHU ENERGIES, Bihar
MOU signed in October, 2012for developing a 50MW solar power project. Submitted proposal to increase capacity to 120MW.
The Kumaragom shelters of 5 MW has been set up in Sivaganga located in Ramanad District of Tamilnadu. The Solar power plant has been operational since January, 2013. The Operation and Maintenance was carried out initially by Kumaragam Shelters and is currently done in-house.
- MoU provides for supply of 5% of net power at variable cost and 30% of power at regulated tariff (as determined by the Appropriate Commission)
- Project Location - Bihar
- Land Acquisition - 300 acres identified and application made for allotment of land
- Power to be evacuated through BPHL 400 kV line
- Consultant appointed for preparing draft EIA report and obtaining TOR from MoEF
VIBHU ENERGIES, TAMILNADU
MOU signed in October, 2014for developing a 10MW solar power project. Submitted proposal to increase capacity to 50MW.
- MoU provides for supply of 30% of net power at variable cost and 70% of power at regulated tariff (as determined by the Appropriate Commission)
- Project Location -Tamilnadu
- Land Acquisition - 60 acres identified and application made for allotment of land
- Power to be evacuated through TANGEDCO110 kV line
- Consultant appointed for preparing draft EIA report and obtaining TOR from DOPTN
VIBHU ENERGIES, DJABOUTTI
Discussion under for developing a 100MW solar power project
MoU provides for supply of 25% of net power at variable cost and 75% of power at regulated tariff (as determined by the Appropriate Commission) with escalation.
- Project Location –Djibouti
- Land Acquisition - 600 acres identified and application made for allotment of land
- Power to be evacuated through EDD400 kV line
- Discussion and further development under process